Execution of the works for the basin, supply/return pipes and the various civil engineering works of the seawater circuit within the complex of the Office Chérifien des Phosphates (OCP) – located in Jorf Lasfar, 19km south of the town of El Jadida; as part of the JORF MP – SAP & ENERGY project.
Water basin with a capacity of 12000 m3 in reinforced concrete including a pumping area (the pumps are not supplied with this batch, their assembly is included in this batch).
- Supply pipe DNN2000mm from the connection points located on the REM3 REM4 pipes nearby.
- Seawater supply line from the basin to the units (SAP and power station).
- Discharge seawater pipe to the existing discharge point "discharge channel".
- Intermediate manholes and reinforced concrete discharge structure.